Project
Management
1. A software
development project was planned to be completed in 12 months. The review of the
project after eight months revealed that Rs. 120000 was spent on the project
for 48% of project completion. Consider the total project budget as Rs 240000.
Calculate and explain the schedule and cost performance index for this
situation. (10 Marks)
Ans:
Introduction
Several types
of software growth projects are within the range of this book. They vary from
repeatable development that has been ended many times earlier than to
critical-edge problem-solving plans. Each presents its challenge to the
designer. The model given below will be the performance area to look at
effective approaches to software expansion project organization. To obtain
products to advertise fast, software growth teams rely on successful plan and
process management to modernize their
2. Take an
example of developing a residential project and carry out the project
feasibility analysis using the six laws of project feasibility. (10 Marks)
Ans:
Introduction
A feasibility
examination is used to decide the feasibility of an idea, such as make sure a
project is legally and officially feasible in addition to economically
justified. It tells us whether a plan is worth the savings in some cases, a
plan may not be possible. There can be several reasons for this, including need
too much income, which avoid those resources from performing other
responsibilities and may price more than a group would earn back by attractive
on a plan that isn't money-making. The growth and respect of project
organizations have changed appreciably over the earlier period few years, and
these modifications are expected to maintain and expand. And with the increase
of project organization come the need for a possible study.
Concept and
application
Laws of
Project Feasibility
Feasibility
examinations
3. You are
given the task of preparing a project plan for the "Annual Day
Function" of your college.
a. Explain the
work breakdown structure and prepare three work breakdown structure levels for
this project plan. (5 Marks)
Ans:
Introduction
Projects come
in all volumes with varying amounts of complexity; however, all unbeaten
projects have an ordinary structure. A project should be designed out and
planned from day one. That's said than completed. There are many workings to
any project, such as its period, its price, and how it will be performed. This
machinery, and more, must be deal with within your project plan. Project
development, then, is about recognizing, prioritizing, and transmission the
tasks and income necessary to
Hello MBA aspirants,
Get MBA assignments of
NMIMS University solved by educational professionals at a nominal charge.
Mail us at: help.mbaassignments@gmail.com
Call us at: 08263069601
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.