(Spring/Feb 2013)
Master of Business
Administration - MBA Semester 4
“Project Management”
Specialization
PM 0016 –Project Risk
Management (4 credits)
(Book ID: B1345)
ASSIGNMENT- Set 1
Marks 60
Note: Assignment Set -1 must be written within 6-8 pages. Answer all
questions.
Q1. Write a note on Process Maturity Model.
Answer : Description of Process Maturity
Process maturity is an indication
of how close a developing process is to being complete and capable of continual
improvement through qualitative measures and feedback. Thus, for a process to
be mature, it has to be complete in its usefulness, automated, reliable in
information and continuously improving.
The maturity of a process or
activity can be defined
Q2. Explain the steps involved in performing risk analysis.10
marks(300-400) words10 marks(300-400) words
Answer : Step 1: Identify the hazards
First you need to work out how
people could be harmed. When you work in a place every day it is easy to
overlook some hazards, so here are some tips to help you identify the ones that
matter:
·
Walk around your workplace and look at what
could reasonably be expected to cause harm.
·
Ask your employees or their representatives what
they think. They may have noticed things that are not immediately obvious to
you. For information on how you can do this please visit our worker involvement
pages.
Q3. Evaluate the tools used to monitor risks 10 marks(300-400) words
Answer : Below is a list of risk
assessment tools available for your use:
Tool Name
|
Description
|
Q4. Explain the six risk management tools .10 marks(300-400) words
Answer : The following diagram
illustrates the six steps of the risk management process: identify, analyze and
prioritize, plan and schedule, track and report, control, and learn. It is
important to understand that the process of
Q5. Assess how and why change fails and analyse the reasons for
resistance to change .10 marks(300-400) words
Answer : Despite the potential
positive outcomes, change is nearly always resisted. A degree of resistance is
normal since change is:
·
Disruptive, and
·
Stressful
Kotter and Schlesinger identified
four key reasons why change is resisted:
Q6. Analyse the event chain methodology.10 marks(300-400) words
Answer : Introduction
In the initial stages of a
project, complex processes and the many risks involved makes it impossible to accurately
model. A model of a project is necessary for efficient project management.
Event Chain Methodology, an
Dear students get fully solved assignments
call us at :- 08263069601
or
mail us at
help.mbaassignments@gmail.com
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.