Dear
students get fully solved assignments
Send
your semester & Specialization name to our mail id :
“
help.mbaassignments@gmail.com ”
or
Call
us at : 08263069601
(Prefer
mailing. Call in emergency )
ASSIGNMENT
DRIVE
WINTER
|
2013
|
PROGRAM/SEMESTER
|
MBADS (SEM 3/SEM 5)
MBAFLEX/ MBAN2 (SEM 3) PGDPMN (SEM 1)
|
SUBJECT
CODE & NAME
|
PM0012 – Project
Finance
|
BOOK
ID
|
B1238
|
CREDITS
|
4
|
MARKS
|
60
|
Note: Answer all questions.
Kindly note that answers for 10 marks questions should be approximately of 400
words. Each question is followed by evaluation scheme.
1 Write short notes on:
Classification of Investment Projects
Investment projects are classified into
three categories on the basis, of the way they influence the investment
decision process: independent projects, mutually exclusive projects and
contingent projects.
Independent projects
An independent project is one, where the
acceptance or rejection does not directly eliminate other projects from
consideration or affect the likelihood of their selection. For example, if management
plans to introduce a new product line, as well as, replace a machine which is
currently producing a different product. These two
2 What it is a project proposal? What are its contents?
Answer:- Definition of project proposal, its purpose
Project proposals are those documents
which are intended to present a plan of action, and list out the reasons for
the necessity of the action with respect to the project to be executed. The
project proposal1 should be in such a way that it convinces the readers in
executing those actions. In most of the cases, this document is prepared either
to serve an internal purpose or when somebody in the firm has an idea on the
ways in which the firm can be profitable and resourceful. Before preparing a
3 MIT Training Ltd. is making an allowance for buying a new online
learning system tofacilitate them to carry out the training they do for their
corporate clients. The traininginstitute is looking at three different systems
with a variety of functionality, and the costof each system is as follows:
System A System B System C
Rs 120,000 Rs 100,000 Rs 85,000
Even though they vary in functionality, however, they differ
moderately in what theyoffer. Although they would all perform the jobs that the
training institute is looking for,they would require the firm to run their
systems very differently and so the expectedcash flows from each system are
very different. The expected net cash flows for eachsystem are as follows:
Year System A System B System C
1 Rs 60,000 Rs 45,000 Rs 15,000
2 Rs 50,000 Rs 30,000 Rs 25,000
3 Rs 60,000 Rs 30,000 Rs 30,000
4 Rs 30,000 Rs 25,000 Rs 48,000
5 Rs 25,000 Rs 15,000 Rs 45,000
Calculate the payback period for each system by using the net cash
flow data.Calculate the average rate of return for each system using the
expected net cash flowdata in the case material.
Solution:-1. Calculate the payback period for each system by using
the net cash flow data.
Payback period =Investment/ Cash
Flow/year
[Answers: system A = 2.2
2. Calculate the average rate of return for each system using the
expected net cash flow data in the case material.
4 Write short notes on
Flexibility valuation
In many projects there are chances where
a project may follow a new path of action to obtain the end result. NPV fails
to capture these typical paths. Where as the DCF models the investment
considering the flexibility and staged nature of investment. The difference
between these two valuation is the “value of flexibility” inherent in the
project.
The two most common flexibility
valuation tools
5 Explain some of the tools and techniques of Cost Management
Answer:- Reason why accurate estimation is required
Project Management has been practiced
since early civilisation. Until 1900 civil engineering projects were normally
managed by creative architects and engineers themselves. It was in the 1950s
that organisations started to systematically apply project management tools and
techniques to complex projects.
6 As there was intense power shortage in Karnataka due limited
power generation in thestate, it became important to explore diverse types of
power generation. As the statehad a mountainous terrain, getting renewable
energy became an apt option. ABCenergy Ltd is one of the largest state owned
energy generator and is committed toexploring a wind farm project. It found a
suitable site before consulting with thecommunity. Then, it started shaping the
project in order to meet the wishes andexpectations of the community during the
process. The consultation started in the monthof May and full permission was
granted within five days of the hearing. The work startedin the month of
November.
There were quite a few challenges which were faced by the team. It
includes working ina physically demanding environment and adhering to the needs
of the landowners, inorder to meet the key project miles stones. Over 20
kilometres of roadways had to beconstructed and the installation of cabling had
to be done. There were several streams,unsuitable oil and soil, and a pipeline
that ran through the site. To carry out the aboveprocesses the ABC energy LTD
estimated an extra amount of about Rs 3 crores. Theproject also faced force meajure
risk like adverse weather conditions with the rainfall.The floods also caused
problems.
The ABC Company and its consultants worked as team to meet the
challenges and cutshorten on their expenditures to meet the budget. The extra
fund of Rs 3 crores wasprovided by the government. A well defined project plan
helped them to provide cleardirection and purpose. The efficient management
team was committed to design andconstruct the project management practises to
develop the plan. Daily managementmeetings were held, which helped the team to
achieve the goals. As a result, the projectteam completed the project in five
days ahead of the estimated timeline and they wereable to show it as a bench
mark to the stakeholders.What were the challenges faced by the project team and
how did they overcomeit?
Answer:-Rule 1: Make Risk Management Part of Your Project
The first rule is essential to the
success of project risk management. If you don't truly embed risk management in
your project, you can not reap the full benefits of this approach. You can
encounter a number of faulty approaches in companies. Some projects use no
approach whatsoever to risk management. They are either ignorant, running their
first project or they are somehow confident that no
Dear students get fully
solved assignments
Send
your semester & Specialization name to our mail id :
“
help.mbaassignments@gmail.com ”
or
Call
us at : 08263069601
(Prefer
mailing. Call in emergency )
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.