Q1. Explain the meaning of Project Deliverables.
What are Project Delays and Its Consequences?
1. Meaning of Project Deliverables
2. Project Delays and Its Consequences
Answer:
Though project deliverables and objectives are
different, there is a very close relationship between the two.
As you know, objectives are what one plans to
accomplish at each phase of the project and ultimately at the time of overall
project completion. In other words, objectives define the purpose of the
project and
Q2. What is Conflict? Explain Types of Conflicts in
a Project.
1. Meaning of Conflict
2. Types of Project Conflict.
Answer:
Each one of us is different in terms of
personality, thinking, behaviour, attitude, goal, interest, etc. A perspective
about a situation often varies from person to person. Such difference in
thinking, perspective, behaviour, etc. often results in conflict between
people. For instance, two people wanting the same object, such as a job or a
house, can lead to a conflict between them. Therefore, we can
Q3. What is the importance of operational
feasibility? Explain the factors that affect operational feasibility. (Mention
the importance of operational feasibility, Discuss the FOUR factors that affect
operational feasibility) 2, 8
Answer: Operating Feasibility: In the previous units, you have
come to understand that feasibility study of aproject is very important from
the point of view of an organisation as it enables an organisation
to assess whether the proposed project is capable of achieving the
desired goals and objectives. Operational feasibility is a part of
project feasibility study, wherein an organisation analyses the extent to
which a proposed project is appropriate for the existing business
Q4. Write short notes on:
1. Precedence Diagramming Method (PDM)
2. Arrow Diagramming Method (ADM)
1. Precedence Diagramming Method (PDM)
2. Arrow Diagramming Method (ADM)
Answer:
1. Precedence Diagramming Method (PDM)
Precedence Diagramming Method (PDM) is one of the
most popular and commonly used methods for arranging activities of a project
visually. In PDM, various project activities are placed inside boxes, termed as
nodes. Thereafter, boxes are connected with the help of arrows. In PDM, the
Q5. What do you understand by cost of quality?
Elaborate on various types of costs of quality associated with a project.
(Write the meaning of cost of quality, Briefly explain each types of costs of
quality associated with a project) 4, 6
Answer: Cost of Quality (COQ): Cost of quality indicates the sum
of conformance cost and non-conformancecost. Conformance means delivering
products that meet the quality requirement of the customer;
whereas, non-conformance indicate the products that are rejected
for not complying with the
Q6. What do you understand by project scope? What
are the various components of project scope? What is scope creep? Explain
various reasons for scope creep.
1. What do you understand by project scope
2. components of project scope
3. What is scope creep
4. reasons for scope creep.
Answer:
scope of a project is considered a critical element
of any
Send your semester & Specialization name to our
mail id :
“ help.mbaassignments@gmail.com ”
or
Call us at : 08263069601
(Prefer mailing. Call in emergency )
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.