PM 0016 –PROJECT RISK MANAGEMENT

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


ASSIGNMENT

DRIVE
SPRING 2016
PROGRAM
MBA
SEMESTER
IV
SUBJECT CODE & NAME
PM 0016 –PROJECT RISK MANAGEMENT
BK ID
B2012
Credit & Marks
4 CREDITS AND 60 MARKS


Note: Answer all questions. Kindly note that answers for 10 marks questions should be approximately of 400 words. Each question is followed by evaluation scheme.


Question. 1. What is Project Risk? Explain different sources of project risk with examples

Answer:Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning, and controlling risk on a project. The objectives of project risk management are to increase the likelihood and impact of positive events, and decrease the likelihood and impact of negative events in the project.

Project Risk identification is the most important process in the Risk Management Planning. Risk Identification determines which risks might affect the project and documents their characteristics. However, we should not spend too much time in identifying risks. After the list is made, qualitative and quantitative analysis is done to figure out which risks you spend time and/or money on.




Question. 2. What is Risk Opportunity and Management System (ROMS)? What are its benefits?

Answer:ROMS is based on 20 years of research and current best practice across a range of high risk industry sectors including construction, mining, security, nuclear power, defence, social and economic infrastructure, ports, health, emergency management, asset management etc

ROMS has been used as the basis for risk and



Question. 3. 1. Using Internet, identify a project and list down all the activities and milestonesof a project and the activity risks associated with these milestones.


Answer:The purpose of this process is to identify the specific tasks needed to be done in order to produce the project's deliverables. This needs to be done in sufficient detail to estimate what resources and time will be required to complete them. The main inputs are the scope baseline consisting of the approved project scope statement, the work breakdown structure, and the WBS dictionary.



2. Using Internet, identify a project and the activity risks associated with it.Categorise the risks into three groups: controllable known, uncontrollableknown and unknown. Find out the percentage of “unknowns” in total risks atthe beginning and towards the end of the project.

Answer:The work package is the lowest level of the WBS is achieved when the work can be accurately estimated (both cost and duration) and can be managed by one individual. The key word here is 'managed', although the work package can be managed by one person, the actual work within the work package may be completed by several people.

For example, One individual could manage




Question. 4. What are the sources of resource risks?

Answer: Resource risks represent less than one-third of the records in the PERIL database. There are three categories of resource risk: people, outsourcing, and money. People risks arise within the project team. Outsourcing risks are due to the use of people and services outside the project team to perform critical project work. The third category, money, is something of an anomaly in the data, as very few of the problems reported were primarily about funding. Money is, however, a key factor in many of the people and outsourcing problems, and



Question. 5. What are different types of scope risks?

Answer: While scope risks represented roughly one-third of the data in the Project Experience Risk Information Library (PERIL) database, they account for close to half of the total impact. The two broad categories of scope risk in PERIL relate to



Question. 6. Explain the three point estimates used in quantitative risk analysis.

Answer:The three-point estimation technique is used in management and information systems applications for the construction of an approximate probability distribution representing the outcome of future events, based on very limited information. While the distribution used for the approximation might be a normal distribution, this is not always so and, for example a triangular distribution might be used, depending on the

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


No comments:

Post a Comment

Note: Only a member of this blog may post a comment.