MBA302 -Legal Aspects of Business

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


ASSIGNMENT

DRIVE
FALL - 2017
PROGRAM
Master of Business Administration - MBA
SEMESTER
Semester 3
SUBJECT CODE & NAME
MBA302 -Legal Aspects of Business
BK ID
B1725
CREDITS
4
MARKS
60


Note: Answer all questions. Kindly note that answers for 10 marks questions should be approximately of 400 words. Each question is followed by evaluation scheme.


Question. 1. What is fiduciary relationship in a contract of guarantee? Explain the kinds of guarantees.

Answer: Business owners know it is very difficult to borrow money for the business from a creditor without a personal guarantee even if the creditor has security against all of the business. If you sign the typical standard guarantee form used by creditors, you may be giving up rights designed to level the field. Some terms of the creditor guarantee are not in your best interest. .



Question. 2.  i) Do you think contract with a minor is valid? Narrate with the help of the facts and judgement in the case: Mohori Bibee v. Dharmodas Ghose.

Answer: The plaintiff, Dharmodas Ghose, while he was a minor, mortgaged his property in favour of the defendant, Brahmo Dutt, who was a moneylender to secure a loan of Rs. 20,000.  The actual amount of loan given was less than Rs. 20,000.  At the time of the transaction the attorney, who acted on behalf of the money lender, had


ii) Explain the rules and remedies for discharge of contract by breach

Answer: A contract may, in some circumstances, be discharged by a breach of contract. Where there exists a breach of condition (as oppose to breach of warranty) this will enable the innocent party the right to repudiate the contract (bring the contract to an end) in addition to claiming damages. A contract cannot be discharged by a breach of warranty.

Anticipatory breach: Where a party



Question. 3. i) Narrate the facts and judgement in the case Howell vs. Coupland.

Answer: The plaintiff contracted with the defendant to buy 200 tons of potatoes grown specifically from the defendant’s land. The defendant’s potato crop was destroyed by disease, rendering the defendant’s performance under the contract impossible. The plaintiff brought suit for damages. The Queen’s Bench ruled in favor of the defendant. The plaintiff appealed.


ii) Who is an unpaid seller? What are the rights enjoyed by an unpaid seller under the extant provisions of law?

Answer: An unpaid seller has two-fold rights, viz.,;

I.      Rights of unpaid seller against the goods, and
II.    Rights of unpaid seller against the buyer personally. We shall now examine these rights in detail.

1.    Rights of Unpaid Seller against the Goods.

Question. 4. The Banking Regulation Act, 1949, provides various methods of regulation of the banking business. Elaborate the key areas of regulation.

Answer: The Banking Regulation Act, 1949 is a legislation in India that regulates all banking firms in India. Initially, the law was applicable only to banking companies. But, 1965 it was amended to make it applicable to cooperative banks and to introduce other changes.

The Act provides a framework using which commercial banking in India is supervised and regulated. The Act supplements the Companies Act, 1956.

Question. 5. Explain the nature and scope of complaints under the Consumer Protection Act?

Answer: (1) A complaint in relation to any goods sold or delivered or agreed to be sold or delivered or any service provided or agreed to be provided may be filed with a District Forum by –

(a)  the consumer to whom such goods are sold or delivered or agreed to be sold or delivered or such service provided or agreed to be provided;

Question. 6. a) Differentiate between a holder and a holder in due course.

Answer: Various differences between holder and holder-in-due-course can be explained on the basis of the following

1. Entitlement: Holder is a person who is entitled for the possession of a negotiable instrument in his own name. Hence he shall receive or recover the amount due thereon. Whereas a Holder-in-due-course is a person who has obtained the instrument for consideration and in good faith and before maturity.

b) Explain the privileges enjoyed by a holder in due course

Answer: Privileges granted to a ‘holder in due course’ under the Negotiable Instruments are given below:

1. He gets a better title than that of the transferor:

One who is a ‘holder’ only gets no better title than that of his transferor but a holder in due course is in a privileged position in that he gets a better title than that of the transferor and the defenses on the part of a person liable that the instrument has been lost, or has been obtained by means of an offence or fraud or for an unlawful consideration cannot be pleaded against a holder in due course (Sec. 58).

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


MBA301 - RESEARCH METHODOLOGY

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


ASSIGNMENT

DRIVE
FALL 2017
PROGRAM
MBA– SEM 3
SUBJECT CODE & NAME
MBA301 - RESEARCH METHODOLOGY
BK ID
B1700
CREDITS
4
MARKS
60


Note: Answer all questions. Kindly note that answers for 10 marks questions should be approximately of 400 words. Each question is followed by evaluation scheme.


Question.1 Define business research and explain the process of research?

Answer:Business research involves establishing objectives and gathering relevant information to obtain the answer to a business issue. You can conduct business research to answer a business-related question, such as: What is the target market of my product? Business research can also be used to solve a business-related problem, such as determining how to decrease the amount of excess inventory on hand. Adequate planning and

Question.2 Discuss Descriptive Research designs? Explain the different kinds of descriptive research designs.

Answer:Sometimes an individual wants to know something about a group of people. Maybe the individual is a would-be senator and wants to know who they're representing or a surveyor who is looking to see if there is a need for a mental health program.

Descriptive research is a study designed to depict the participants in an accurate way. More simply put, descriptive research is all about describing people who take part in the study.


Question.3 Discuss four types of measurements scales with appropriate examples.

Answer:There are four measurement scales (or types of data): nominal, ordinal, interval and ratio.  These are simply ways to categorize different types of variables.  This topic is usually discussed in the context of academic teaching and less often in the “




Question.4 Differentiate between the Stratified random sampling and Systematic sampling.

Answer:Simple random samples and stratified random samples differ in how the sample is drawn from the overall population of data. Simple random samples involve the random selection of data from the entire population so that each possible sample is equally likely to occur. In contrast, stratified random sampling divides the population into smaller groups, or strata, based on shared characteristics. A random sample is taken from each stratum in



Question.5 Distinguish between coding closed-ended structured questions and coding open-ended structured questions

Answer:The main difference between a closed-ended question and an open-ended question is the type of response that can be given. With a closed-ended question there are a limited number of choices to choose from when answering, but with an open-ended question the respondent can answer in their own words allowing for a wide variety of answers.


Question.6 Explain the Structure of the Research Report. What are the guidelines for effective report writing?

Answer:The major difference amongst the types of reports is that all the elements that make a research report would be present only in a detailed technical report.

Usage of theoretical and technical jargon would be higher in the technical report and visual presentation of data would be higher in the management report. In the management report, the sequencing of the report might be reversed to suit the

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


MBA206 - Project Management

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601

ASSIGNMENT

DRIVE
FALL 2017
PROGRAM
Masters of Business Administration - MBA
SEMESTER
II
SUBJECT CODE & NAME
MBA206 - Project Management
BK ID
B1627
CREDITS
4
MARKS
60


Note: Note –The Assignment is divide into 2 sets. You have to answer all questions in both sets. Average score of both assignments scored by you will be consider as your IA score. Kindly note that answers for 10 marks questions should be approximately of 400 words.


ASSIGNMENT SET-1

Question. 1. Define Project Management Body of Knowledge (PMBOK). Detail nine knowledge areas of Project Management Body of Knowledge (PMBOK).

Answer: There’s a lot to learn as a project manager! A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition breaks down what project managers need to know to successfully pass their PMP® exam and also be effective in the role.

There are 10 project management knowledge areas covered by the PMBOK® Guide. They cover each of the 47 project management processes. This


Question. 2. Elaborate five project life cycle phases.

Answer: Project management broadly refers to the process and related activities of planning, organizing and controlling resources to achieve specific goals. Projects are usually constrained by factors such as scope, budget and time, requiring the project management function to optimize the allocation of resources and properly integrate them to overcome these constraints and meet predefined objectives. Managing project activities can be seen as a sequence of steps to be completed, in line with the five phases that define the project life cycle.

1.       Initiation: Project initiation starts the project life cycle and involves assembling a team headed by a project manager and providing an overview of the project. The overview typically includes defining the reason for the project, business goals and the strategy to achieve the desired results. In addition, a preliminary scope, budget proposal, milestones and a completion date are given.

Question. 3. Define the determination of the Critical Path

Answer: Critical Path is a term from the field of project management describing a set of tools and a methodology.

The technical definition of the critical path in a sequence of networked work packages is the path with the least amount of slack. In practical terms, this path is the sequence of events that if any are delayed, will delay the entire project. And in even simpler terms, the critical path is the sequence of tasks that will take the longest to complete to deliver the project.



ASSIGNMENT SET-2


Question. 1. Illustrate strategies to control the project risk.

Answer: The things that might go wrong are called project risks, and a wise project manager identifies them early at the beginning of the project so that he or she can do something about them. Of course, risk management is an ongoing activity, so you should carry on identifying and recording new risks as they come up.

Creating a list of risks is a good starting point, but it isn’t enough in itself. You also need an action plan per risk in order to be able to manage them

Question. 2. Detail the planning process of PMIS.

Answer: Project Management Information System (PMIS) are system tools and techniques used in project management to deliver information. Project managers use the techniques and tools to collect, combine and distribute information through electronic and manual means. Project Management Information System (PMIS) is used by upper and lower management to communicate with each other.

Project Management Information System (PMIS) help plan, execute and close project management goals. During the planning process, project managers use PMIS for budget framework such as estimating costs. The Project Management


Question. 3. What is Project Performance Evaluation? Elaborate types of project performance evaluation.

Answer: In order for businesses to successfully initiate, develop and complete projects, they need to recruit, hire and train people with solid project management skills. The business world is speeding up and product lifecycles are much shorter. This is forcing organizations to start new projects at an increasing rate. However, as projects become more complex, project failures, delays, and missed deadlines are becoming increasingly common.

One of the main factors leading to the increasing complexity of projects is the rise of globalization. It is a challenging task for organizations to operate and coordinate projects in different countries around the world due to differences in time

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601


MBA205 & OPERATIONS RESEARCH

Dear students get fully solved assignments
Send your semester & Specialization name to our mail id :
help.mbaassignments@gmail.com
or
call us at : 08263069601

DRIVE
FALL 2017
PROGRAM
MASTER OF BUSINESS ADMINISTRATION (MBA)
SEMESTER
II
SUBJECT CODE & NAME
MBA205 & OPERATIONS RESEARCH
CREDITS
2, 4 CREDITS
MARKS
30


Note: Answer all questions. Kindly note that answers for 10 marks questions should be approximately of 400 words. Each question is followed by evaluation scheme.


Assignment Set -1

Question 1 Define the Linear programming problem in operation Research. Also, explain various assumptions, advantages and limitations of linear programming problem.
A Linear programming problem in operation Research
Assumptions of linear programming problem
Advantages of linear programming problem
Limitations of linear programming problem

Answer: In organisations, managers are required to make judicious use of scarce resources, such as men, materials, machines and capital, to minimise costs and maximise profits. A technique that is used to select the best alternative from a set


Question 2 a. Discuss the concept of Degeneracy in transportation problem
b. The ABC Tool Company has a sales force of 25 men who work out from Regional offices. The company produces four basic products lines of hand tools. Mr. Jain, the sales manager, feels that 6 salesmen are needed to distribute product line 1, 10 salesmen are needed to distribute product line 2, 4 salesmen to product line 3 and 5 salesmen to product line 4. The cost per day of assigning salesmen from each of the offices for selling each of the product lines are as follows;
Regional office
Product Lines
𝑷𝟏
𝑷𝟐
𝑷𝟑
𝑷𝟒
R1
20
21
16
18
R2
17
28
14
16
R3
29
23
19
20
Now, 10 salesmen are allowed to office R1, 9 salesmen to office R, and 7 salesmen to office R.
How many salesmen should be assigned from each office to selling each product line in order to minimize costs?
Degeneracy in transportation problem
Optimum allocation.
Optimum transportation cost

Answer: a) Degeneracy in transportation problem
A basic solution to an m-origin, n destination transportation problem can have at the most m+n-1 positive basic variables (non-zero), otherwise the basic solution degenerates. It follows that whenever the number of basic cells is less than m + n – 1, the transportation problem is a degenerate one. The degeneracy can develop in two ways:

Case 1 - The degeneracy develops while



Question 3 a. Elaborate the meaning of Simulation.
b. What are different Practical applications of simulation
A Meaning of Simulation.
Practical applications of simulation

Answer: a) Simulation is a representation of real-life situations. It is a method in which a replica of a real-world process or system is developed over a period of time. The simulated model acts in the same manner as the selected physical or abstract process or system behaves in reality. For example, aircraft pilots are given training through simulation models as training with real aircrafts can incur huge costs as well as involve various risks. Similarly, in education sector, teachers are trained on the simulated models of students (a group of individuals who imitate as students). This avoids the risk of spoiling the future of students if the teacher is not able to




Assignment Set -2
Question 1 a. Define the meaning of assignment problem in operation Research.
b. A Departmental head has four subordinates and four task to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimate of the times each man would take to perform each task is given in the following matrix-
Tasks
Subordinates
I
II
III
IV
A
8
26
17
11
B
13
28
4
26
C
38
19
18
15
D
19
26
24
10
How should the tasks be allocated to subordinates to minimize the total man-hours?
A Description of assignment problem
Optimum allocation through Hungarian method

Answer: a) An assignment problem is a special type of transportation problem. In an assignment problem, the same number of facilities (sources of supply) needs to be allocated to the same number of jobs (points of destinations) so that the transportation cost is minimised or the profit is maximised. An assignment problem can occur while assigning:
·       Machines to factory orders
·       Salespeople to sales territories
·       Teachers to classes
·       Police vehicles to patrolling areas
·        

Question 2. Define following criteria’s used for decision making under Uncertainty
a. Optimism (maximax or minimin) criterion
b. Pessimism (maximin or minimax) criterion
c. Equal probabilities (Laplace) criterion
d. Coefficient of optimism (Hurwicz) criterion
e. Regret (salvage) criterion

Answer: a) Optimism (maximax or minimin) criterion: Here, the decision maker tries to achieve the largest possible profit (Maximax) or minimum possible cost (minimin). If the entries in the payoff matrix are the one which the decision maker wants as large as possible, for example, profits or sales revenue, he/she selects the alternative that represents the maximum of the maximum payoff. In case where the entries of the payoff matrix are one which the decision maker wants as small as possible, he/she goes for the minimum of the



Question 3 a. Explain the importance and utility of the replacement model in business organizations.
b. The maintenance cost and re-sale value per year of a machine whose purchase price is Rs. 7000 is given below-
Year
1
2
3
4
5
6
7
8
Maintenance cost (Rs.)
900
1200
1600
2100
2800
3700
4700
5900
Resale value (Rs.)
4000
2000
1200
600
500
400
400
400
Importance and utility of the replacement model Replacement Year

Answer: a) In an organisation, replacement problems arise when fixed assets, such as machines, equipment, and other tools, need to be replaced due to reduced efficiency, failure or breakdown. Sometimes, replacement takes place when more efficient equipment is available in the market or the maintenance of the existing equipment is incurring a huge cost on an organisation. However, an organisation needs to decide when the